From hours to cost and margin: what is missing
A recorded hour is not yet an amount in euros. To reach an economic analysis, other information is needed, and it helps to distinguish three levels.
|
|
|
Three levels to tell apart
Level 1: time. These are the hours recorded on the job's tasks. They tell us how much time was attributed to the work, not how much it cost.
Level 2: costs. Time becomes labor cost only if it is linked to an hourly cost. The cost of the job also includes other items, such as materials and work outsourced externally.
Level 3: margin. It is obtained by comparing the job's revenue with the costs we decided to consider. The result depends on which costs we included.
Each level builds on the previous one but does not replace it.
From time to labor cost
In the example, the hours recorded on cutting and assembly are the basis for calculating the job's labor cost. This requires an hourly cost, and there is no single way to calculate it. It can be just the personnel cost per hour, or a rate that also includes machines, space and energy of the department. Different measures serve different purposes, and using them without distinguishing them leads to errors.
Times must also be read with caution. As happens, for example, on construction sites, people working on several jobs may not record their activity precisely, and the labor cost attributed ends up imprecise. This is another reason to run the checks in the section on recorded times.
From labor cost to job cost
Labor cost Recorded hours × hourly cost | + | Materials For example, the parts to cut | + | External work Work outsourced to third parties | + | Indirect costs Administration, shared spaces |
Labor cost alone is a partial cost. A job also includes other items:
- Materials: for example, the parts to be cut.
- External work: work outsourced to third parties.
- Indirect costs: expenses that cannot be attributed to a single job, such as administration or shared spaces.
The sources distinguish successive levels of cost. They start from prime cost, meaning direct costs. Indirect production costs are added, then general costs. Indirect costs are allocated to jobs using different criteria, including actual labor hours. Each criterion has justifications and drawbacks.
Here times make a concrete contribution: they can serve as a basis for allocating part of the costs. To do so, however, a criterion and the items to be allocated must be chosen.
From cost to margin
Margin is the difference between revenue and the costs considered. If we subtract only direct costs from revenue, we get a partial result. One source calls it contribution margin and warns that it is not the net result of the job. For a complete picture, the allocated indirect costs are also needed.
So, when we talk about margin, it is always best to state which costs were subtracted. Two margins calculated with different items cannot be compared.
Reading mistakes to avoid
× Fewer hours ≠ more profitable Revenue, materials and other costs also matter | × More hours ≠ a loss It depends on what was charged and what the job included | × Times ≠ productivity They show time attributed, not useful work done |
- A job with fewer hours is not necessarily more profitable. Revenue, materials and other costs also matter.
- A job with more hours is not necessarily a loss. It depends on how much was charged and on what was included in the work.
- Times alone do not measure productivity. They tell us how much time was attributed, not how much useful work was done.
What to ask whoever handles the accounts
1 Hourly cost Which one do we use, and what does it include? | 2 Other direct costs Which ones does the job have? | 3 Indirect costs How do we allocate them? | 4 Revenue What do we compare, and against which costs? |
To move from hours to economic analysis, a company can ask four questions:
- Which hourly cost do we use, and what does it include?
- Which other direct costs does the job have?
- How do we allocate indirect costs?
- Which revenue do we compare, and against which costs?
These are questions for whoever handles the accounting, not for the department. The answers come from other systems and from choices that the company must make explicit.
Before using the data: five questions
After reading the times, it is worth pausing on five questions. If we cannot answer one of them, the right step is to collect the missing information, not to force a conclusion.
| Is the question clear? What we want to understand, about which work and for what purpose. |
| Does the data cover the work? Tasks, period and status of the job. |
| Is the comparison consistent? Same tasks, same measure, same period, same work. |
| Have we separated the difference from its explanations? What we observed and what remains to be verified. |
| For the economic analysis, are the items defined? Hourly cost, other costs, revenue, and whether the margin is partial or complete. |
Job times are a starting point. They help us ask more precise questions about the work and understand what other information is needed. The answers and decisions depend on each company's organization.
For information on Osti solutions for recording work times and managing jobs, contact us.